Certified RAID & Status Reporting Practitioner

Prove you can run a RAID log and a weekly status report the way senior delivery managers do. Free course, a practical task in the RAID Log Builder, a proctored exam and a verifiable certificate.

₹2,500 · $40 outside IndiaIncludes 1 year of Tools Pro30 questions · 45 min · 60% to pass
Loading your certification status…

The course: nine topics

Free to read. Each topic is one section of the exam, so this is also your study guide. About two hours in total.

Topic 1 of 9

RAID fundamentals

What each letter means, how a RAID log differs from a project plan, and why it must be a living register.

  • Risk: might happen. Issue: already happening. Assumption: believed true but not confirmed. Dependency: something you need from outside your team.
  • Agree with the client at the start whether "D" means Dependencies or Decisions, and track both explicitly either way.
  • Start the log at mobilisation and keep it live until closure; the delivery manager owns the log, a named role owns each item.

"The vendor might deliver the API late" is a risk.

"The API environment is down today" is an issue.

Topic 2 of 9

Writing good risks

Cause, risk event, effect, with a mitigation that is an action and a contingency for when it happens.

  • Write: "Because <cause>, <event> may happen, leading to <effect>."
  • A mitigation reduces likelihood or impact before the risk happens; "monitor" is not an action.
  • Choose a response: avoid, reduce, transfer or accept, and record a contingency for high-impact risks.

Weak: "Clearinghouse risk."

Strong: "Because the clearinghouse certification slot is not booked, certification may finish after cutover, delaying go-live by two weeks."

Topic 3 of 9

Assumptions

Turning planning beliefs into checked facts before the plan depends on them.

  • Write assumptions so they can be checked: who, what, when.
  • Give each one an owner and a validation date; close it with who confirmed it.
  • If an assumption proves false, raise a risk or issue for the impact and re-plan.

Weak: "Testers are available."

Strong: "The client's UAT team of four is available full-time for the three-week UAT window starting 2 March."

Topic 4 of 9

Issues

Recording, prioritising, working around and escalating problems that are already happening.

  • Record what is happening, its impact and who owns the resolution; link the risk it came from.
  • Rate issues by impact and urgency; escalate when a milestone is threatened or the team cannot resolve it in time.
  • A workaround keeps work moving; the closure note says what fixed it, when, and who confirmed it.

Closure note: "Resolved 14 Oct: client IT granted VPN access to all 8 testers; testing resumed the same day (confirmed by QA lead)."

Topic 5 of 9

Dependencies

Tracking what you need from vendors, the client and other teams, before it becomes an issue.

  • Name the provider, what is needed, the date needed and what it blocks.
  • Watch the gap between "needed by" and "promised by"; a negative gap is an early warning.
  • Review dependencies due in the next two to four weeks every week; a late one becomes a linked issue.

"Payment switch vendor to certify NEFT/RTGS message changes by 20 Nov, needed before SIT cycle 2."

Topic 6 of 9

Rating and the heat map

Impact × likelihood on a 3 × 3 scale, agreed definitions, and reading the exposure heat map.

  • Score = impact × likelihood (High 3, Medium 2, Low 1); High × High = 9 needs attention now.
  • Write down what High, Medium and Low mean for your project so the team rates consistently.
  • Re-rate after every change and after mitigations complete; plot open risks and issues on the heat map.

A High-impact, Low-likelihood risk stays visible with a contingency plan; it is not closed just because it is unlikely.

Topic 7 of 9

Owners, actions and review

Who does what by when, and a weekly review that keeps the log honest.

  • Owners are named roles, never "team" or "TBD"; actions say who, what, by when and how we know it is done.
  • Weekly review: new and changed items first, then top risks, then overdue actions.
  • Close items with a note; keep closed items for history, audits and lessons learned.

Weak action: "Follow up."

Strong action: "Integration Lead to confirm sandbox access with bank IT by Thu 17 Oct."

Topic 8 of 9

Weekly status and RAG

Green, amber and red with clear definitions, a summary that leads with what matters, and no watermelons.

  • Green: on track. Amber: at risk, recovery within the team's control. Red: will miss without help or a decision from above.
  • Report overall, schedule, scope and quality; include top risks and issues, overdue actions and dependencies due soon.
  • Ask for decisions with options, impact, your recommendation and the date needed; show the week-over-week trend.

A "watermelon" report is green outside and red inside. Amber early is better than red as a surprise.

Topic 9 of 9

Governance and real situations

Steering committees, escalation, change control and go/no-go decisions in practice.

  • Steering committees decide priorities, escalated risks, scope and budget; they are not for task updates.
  • Escalate early with facts, options and a recommendation; take new requests through change control.
  • Go/no-go uses agreed criteria; after hypercare, hand over open items and capture lessons learned.

Critical defect in a non-core feature two days before go-live: propose going live with that feature switched off, a hotfix plan and sponsor approval.

The practical task

  1. Open the RAID Log Builder and create a log for a real or realistic project, with at least 3 entries of each type.
  2. Give every entry a rating, an owner role, an action and a due date.
  3. Write that week's status report with Weekly status: ratings, summary, done, next and decisions needed.
  4. Export the PowerPoint deck and email it to businessdomainlab2026@gmail.com with the subject "RAID certification task".

Remove client names or confidential details before you send it. We reply within three working days.

The assessment

Format

30 questions · 45 minutes

Multiple choice, drawn from all nine topics, proctored online with your webcam.

Pass mark

60%

The first attempt and one retake are included. Retakes open 7 days after an attempt.

Certificate

Verifiable

Numbered, with a QR code, checkable by employers at businessdomainconnect.com/verify.

Common questions

What do I get for ₹2,500?

The BDC Certified RAID & Status Reporting Practitioner assessment (with a free retake), a verifiable certificate if you pass, and one year of BDC Tools Pro: 100 AI drafts a month, Excel export and clean PowerPoint slides. Outside India it is $40.

How is the assessment run?

30 multiple-choice questions in 45 minutes, online and proctored with your webcam, the same way as BDC domain certifications. The pass mark is 60%. A power cut or dropped connection does not cost you the attempt.

What is the practical task?

Build a RAID log for a real or realistic project in the RAID Log Builder, write that week's status report, and email the exported PowerPoint deck to us. We check it before the certificate is issued.

Is the course free?

Yes. All nine topics are free to read on this page. You pay only for the assessment, the certificate and the year of Tools Pro.

Can I get a refund?

Yes, in full within 7 days of paying, if you have not started the assessment or sent the practical task, and have used no more than 5 AI drafts. See the Refund & Cancellation Policy at businessdomainconnect.com/refund-policy.

Can an employer check my certificate?

Yes. Every certificate has a number and a QR code that anyone can check at businessdomainconnect.com/verify.

← All BDC tools · Certification standard